| Project |
Type of investment |
Total investment (RMB) |
Date of commercial operation |
Average annual Power generation capacity (kWh) |
| Suzhou Waste Landfill Methane-to-energy Project Phase I |
BOO for 25 years |
27,940,000 |
August 2006 |
>18,000,000 |
| Suzhou Waste Landfill Methane-to-energy Project Phase II |
BOO for 23 years |
12,750,000 |
September 2008 |
>9,000,000 |
| Shenzhen Rooftop Photovoltaic Energy Project |
BOO for 25 years |
27,917,000 |
November 2010 |
>1,480,000 |
| Zhenjiang Ground Photovoltaic Energy Project |
BOO for 25 years |
73,490,000 |
December 2010 |
>4,059,000 |
| Suqian Rooftop Photovoltaic Energy Project |
BOO for 25 years |
52,720,000 |
December 2010 |
>2,205,000 |
| Dangshan Biomass Power Generation Project |
BOO for 25 years |
312,468,000 |
September 2011 |
>184,000,000 |
|
|
|
|
|
|
| |
| Project |
Type of investment |
Total investment (RMB) |
Date of commercial operation |
Average annual Power generation capacity (kWh) |
| Zibo Heat Pump Project Phase I |
BOO for 20 years |
57,887,000 |
Completing of external construction in October 2010 |
N/A |
| Huaining Ground Photovoltaic Energy Project |
BOO for 26 years |
50,470,000 |
March 2011 (expected) |
>2,170,000 |
| Xinyi Biomass Power Generation Project |
BOO for 25 years |
321,040,000 |
2012 (expected) |
>184,000,000 |
| Shuyang Biomass Cogeneration Project |
BOO for 25 years |
339,610,000 |
2012 (expected) |
Power: >172,250,000 Heat: >390,000 tonnes |
| Linyi Biomass Power Generation Project |
BOO for 25 years |
320,000,000 |
2012 (expected) |
>184,000,000 |
| Suzhou Leachate Methane-to-energy Project |
BOO for 20 years |
7,956,000 |
2012 (expected) |
>5,250,000 |
|
|
|
|
|